Assess filling room labour for shared Spanish beverage brands

Estimate shared-brand filling room labour in Spain using task time, crew requirements and responsibility for client packaging.

Italiano

Separate the hours needed to run the line from the handover of brand-owned bottles and labels. Assign who confirms the materials, clears the previous brand and releases the next one. Use observed times and simultaneous staffing by task.

Convert one cross-brand run into labour hours

Hypothetical Spanish site example, assuming tasks do not overlap
TaskExample staffing and timeHours
Running the agreed batchTwo operators × 2 hours4.0 person-hours
Clear and return customer materialsTwo people × 30 minutes1.0 person-hour
Verify lot, label and first accepted unitsOne quality role × 30 minutes0.5 person-hour
Total for this assignment4 + 1 + 0.55.5 person-hours

If a person covers two tasks together, allocate the actual time once. Put “marca”, “lote” and “responsable” in the handover sheet so packaging and label responsibility stays with the right party when shifts change.

The Spanish format comparison guide helps identify the equipment dependencies behind each brand’s change.