Capture the actual route and utilities at the receiving site while the bottling cell is still installed at origin. Use a site-approved plan with dated photos and responsible people. Record open checks in Spanish so collection and installation teams can follow the same list.
Copy these Spanish headings into the site record
| Spanish label | Evidence to collect | Decision |
|---|---|---|
| Acceso y paso libre | Door and turn dimensions, obstructions and dates | Confirm each packed module can be moved by the qualified provider |
| Puntos de conexión | Air, water, power and drainage location and verified duty | Assign check or adaptation |
| Zona de maniobra y montaje | Areas for staging and approved site work | Assign timing and access responsibility |
| Pendientes y responsables | Measured source, named role and due date | Hold commitment where a dependency is unverified |
For example, a documented crate width of 1.95 m exceeds a measured clear door width of 1.90 m. Escalate that measurement before booking transport and have the qualified team verify an alternate route or scope.
The Spanish integration and commissioning guide links site evidence with the receiving work.
Send the Spanish site record and the packed module dimensions